When a permit is required
Permit triggers and exempt work for Jeannette
The City enforces the PA UCC and zoning rules for accessory structures including pools, fences, sheds, and garages; public forms cover zoning permits, residential building permits, manufactured homes, demolition, sidewalks, signage, swimming pools, and commercial occupancy.
- Exempt Privacy fence under 6 feet
- Exempt Residential retaining walls under 4 feet
- Exempt For owner occupied structures, the City's rental occupancy inspection program does not apply
- Completed permit form
- Plans where required
- Three sets of sealed plans prepared by a licensed architect or engineer for commercial building permits
- Electrical inspection reports before certificate of occupancy
- Building code
- Pennsylvania Uniform Construction Code
- Contractor requirements
- Electrical inspections and fees are the responsibility of the owner or contractor and reports must be submitted to the City building code official; PA home improvement contractor registration rules still apply where applicable.
Application process
Typical processing: Rental occupancy requests are typically scheduled through the Tax Office; lien and zoning certificate requests are typically completed within 24 hours of receipt and payment; no general building permit turnaround was published
- 01 Select the correct permit form from the City Forms and Permits page.
- 02 Complete the form and mail or drop it off to City Hall at 110 S. 2nd Street.
- 03 For occupancy inspections, call or stop at the Tax Office to schedule the inspection and pay before inspection.
- 04 For commercial occupancy, contact the Code Enforcement Officer directly before beginning the process because the City notes it can be more detailed.
- 05 The City or Fire Department performs the inspection, issues corrections if needed, and emails the permit or occupancy document once the property passes.
Typical processing time: Rental occupancy requests are typically scheduled through the Tax Office; lien and zoning certificate requests are typically completed within 24 hours of receipt and payment; no general building permit turnaround was published
Fee schedule
Effective 2021
Jeannette says forms may be mailed or dropped off and occupancy inspection payments can be made in person or by mail; checks should be payable to the City of Jeannette
Fees change periodically. Confirm at the official fee schedule ↗ (effective 2021) before budgeting.
Required inspections
Scheduling and sequence
- Tax Office (phone)
- Tax Office (in-person)
- Inspection hours
- 7:30 a.m. to 3:30 p.m. Monday through Friday
Typical sequence: City fee schedule lists footing, foundation, sanitary underground, rough framing, rough plumbing, rough mechanical, energy, drywall, plumbing final, mechanical final, and overall final; electrical rough-in, service, and final are separate third-party reports.
Frequently asked
Common questions about Jeannette permits
01 Do I need a building permit in Jeannette, PA? ▸
02 How much does a building permit cost in Jeannette, PA? ▸
03 How do I apply for a building permit in Jeannette, PA? ▸
04 How long does it take to get a building permit in Jeannette, PA? ▸
05 What work is exempt from building permits in Jeannette, PA? ▸
06 How do I schedule a building inspection in Jeannette, PA? ▸
Educational reference. Permit rules and fees change — confirm current requirements directly with Code and Zoning Enforcement Office before applying. Jaspector is not legal advice.